Friday, 10 February 2017

Busy week!

Its been a busy week at the block. They finished the roof in record time working throughout the hot weather. I visited again at the end of the week thinking nothing was being done as the electrician was due on Thursday. I got a surprise when I arrived at the block. It had been cleaned up, eaves installed, electrician and NBN rough in complete and kitchen marked out, range hood flue in. Now we are waiting on insulation and then pre-lock up stage will be complete. Next will be lock up stage when the doors, plaster and garage door get installed.  It was wonderful walking through it.
Eaves

view from street under construction. usually filled with tradies cars.

Bricks cleaned. Bricks to be rendered have been left uncleaned. 

view to the end of the street

Our backyard

Monument roof and windows, surfmist fascia, chiffon Urban one brick.